北京市规划和自然资源委员会西城分局
建设工程规划核验(城镇居民建房)
TEXC111122223333013110712031000
0
916af078-132f-4f92-84ba-a39987c70c3c
df22a41e-4fd9-4af2-8e30-fbca69716215
3
07
市规划自然委西城区分局
110102000000
北京市规划和自然资源委员会西城分局
西城区政务服务中心:法定工作日: 上午: 09:00 - 12:00; 下午: 13:30 - 17:00; (延时服务时间: 工作日上午08:30 - 09:00; 中午12:00 - 13:30; 下午17:00 - 17:30; 周六上午08:30 - 12:30; )
西城区政务服务中心:北京市西城区西直门内大街275号二楼综合窗口
未经验收或者验收不合格的建设工程,规划自然资源主管部门不予办理不动产登记手续(来源:北京市城乡规划条例 第四十三条)
申请与受理: (1)办理规划验收请通过申请人或委托代理人现场提交申报材料(其中委托代理人申报的,应在窗口申报时提交经过公证的授权委托书)。申请人应当对提交的申报材料实质内容及真实性负责,并依法承担相应法律责任。 (2)对符合申报要求的,服务窗口予以受理。对不符合申报要求的,出具不予受理通知书。需要补齐补正的,出具补齐补正通知书。(3)《建设工程规划许可证》文号内含“简建居字”的城镇居民建房的规划验收,请通过社会投资简低低风险“一站通”服务系统平台(网址:http://tzxm.beijing.gov.cn/slre/index)申请办理,无须参照本指南。
{"IS_GUIDE":"1","ONLINE_DECLARE_SYSTEM_MODE":"99","ITEM_REALITY_USELEVEL":"","SERVICE_OBJCT":"","IS_CONSTRUCTION":"1","CL_SERVICE_TYPE":"","APP_CODE_ID":"","YESNO_CITY_UNICOM":"0^1","CROSS_AREA":"","ISSHOHCENTER":"0","WECHAT_CODE_ID":"","FINANCIAL":"","LITTLEPROGRAM_CODE_NAME":"","CROSS_AREA_ALL":"","CROSS_PROVINCE":"","ALIAS_NAME":"[\"建设工程规划核验(城镇居民建房)\"]","EAR_DISABILITY_GRAD":"","LIB_DISABILITY_GRAD":"","SPEAK_DISABILITY_GRAD":"","REGISTER":"","ONLINE_HANDLING_DEPTH_STANDARD":"05","APPROVAL_TYPE":"1","MIND_DISABILITY_GRAD":"","ACCEPTSERVICE":"99","YWBLX_ID":"df22a41e-4fd9-4af2-8e30-fbca69716215","ONLINE_DECLARE_SYSTEM_DEPT":"","CONSTRUCTION_EXPANSION":"","EMPOWER":"0","EXEMPT_MATERIALS":"","LITTLEPROGRAM_CODE_ID":"","EYE_DISABILITY_GRAD":"","ISMONVEINCENTER":"0","DATA_FLAG":"","BUSINESS_APPROVAL_DEPT":"北京市规划和自然资源委员会","POWER_NAME":"建设工程规划核验(城镇居民建房)","ITEM_ATTRIBUTE":"04^05^11","CROSS_AREA_ATEXT":"","AGE":"","BGSYSTEM_APPROVAL_OTHER":"北京市规划自然资源委员会项目审批办事服务平台","WIT_DISABILITY_GRAD":"","WECHAT_CODE_NAME":"","POWER_CODE":"H1203500","DISABILITY_TYPE":"","IS_ENABLE_CERTIFICATE_SHARE":"0","POWER_ATTRIBUTE":"1","ONLY_ID":"2215d819-81ed-11ea-8de7-fa163e4f9ad9","YES_NO_OPEN":"1","BGSYSTEM_APPROVAL_NAME":"其他","APP_CODE_NAME":"","HOLDER":"","VERSION":"20241125"}
[{"ID":7842438,"TASKGUID":"916af078-132f-4f92-84ba-a39987c70c3c","T_ID":"f858d826-f75d-45d1-847a-01fd32acecbd","P_ID":"","NAME":"是否为房屋跨度超过6米的平房或房屋二层(含)以上及整体院落改造","NODE_LEVEL":1,"NODE_PATH":"/f858d826-f75d-45d1-847a-01fd32acecbd","CHILD_COUNT":2,"ORDER_NUM":1,"SERIAL_NUMBER":"1","CONDITION_ATTR":"01","IS_RADIO":"1","IS_SUPPORT":"","SUMMARY":"1 是否为房屋跨度超过6米的平房或房屋二层(含)以上及整体院落改造\n\t1.1 否\n\t1.2 是","CD_TIME":"Dec 4, 2025 3:45:55 PM","CD_BATCH":"2025120400019","DISTRIBUTETAG":"all-data^investment^TEXC11112222333301^110102000000^construction^11110000MB1503996K^non-construction_expansion","DATAJSONTEXT":"{\"VERSION\":\"20220810\",\"TREE_TYPE\":\"\",\"CONSULTATION_QA\":\"\"}","parOrder":"","proOrder":"1","newOrderNum":"001","itemGuideConditionRelatedList":[]},{"ID":7842436,"TASKGUID":"916af078-132f-4f92-84ba-a39987c70c3c","T_ID":"4c123414-92b8-480a-9792-46f0884fd6bd","P_ID":"f858d826-f75d-45d1-847a-01fd32acecbd","NAME":"否","NODE_LEVEL":2,"NODE_PATH":"/f858d826-f75d-45d1-847a-01fd32acecbd/4c123414-92b8-480a-9792-46f0884fd6bd","CHILD_COUNT":0,"ORDER_NUM":1,"SERIAL_NUMBER":"1.1","CONDITION_ATTR":"02","IS_RADIO":"","IS_SUPPORT":"","SUMMARY":"","CD_TIME":"Dec 4, 2025 3:45:55 PM","CD_BATCH":"2025120400019","DISTRIBUTETAG":"all-data^investment^TEXC11112222333301^110102000000^construction^11110000MB1503996K^non-construction_expansion","DATAJSONTEXT":"{\"VERSION\":\"20220810\",\"TREE_TYPE\":\"\",\"CONSULTATION_QA\":\"\"}","parOrder":"","proOrder":"","newOrderNum":"001.001","itemGuideConditionRelatedList":[]},{"ID":7842437,"TASKGUID":"916af078-132f-4f92-84ba-a39987c70c3c","T_ID":"5f24db1b-e94a-43a8-ad79-3ad45f90c676","P_ID":"f858d826-f75d-45d1-847a-01fd32acecbd","NAME":"是","NODE_LEVEL":2,"NODE_PATH":"/f858d826-f75d-45d1-847a-01fd32acecbd/5f24db1b-e94a-43a8-ad79-3ad45f90c676","CHILD_COUNT":0,"ORDER_NUM":2,"SERIAL_NUMBER":"1.2","CONDITION_ATTR":"02","IS_RADIO":"","IS_SUPPORT":"","SUMMARY":"","CD_TIME":"Dec 4, 2025 3:45:55 PM","CD_BATCH":"2025120400019","DISTRIBUTETAG":"all-data^investment^TEXC11112222333301^110102000000^construction^11110000MB1503996K^non-construction_expansion","DATAJSONTEXT":"{\"VERSION\":\"20220810\",\"TREE_TYPE\":\"\",\"CONSULTATION_QA\":\"\"}","parOrder":"","proOrder":"","newOrderNum":"001.002","itemGuideConditionRelatedList":[{"ID":26476564,"TASKGUID":"916af078-132f-4f92-84ba-a39987c70c3c","T_ID":"5f24db1b-e94a-43a8-ad79-3ad45f90c676","G_ID":"08ea2201-1081-4ff7-b194-f26f79643085","M_CODE":"400398","MATERIAL_ID":"3930b5ae-9cd2-49e5-95c8-8e49f2de6d62","CD_TIME":"Dec 4, 2025 3:45:55 PM","CD_BATCH":"2025120400019","DISTRIBUTETAG":"all-data^investment^TEXC11112222333301^110102000000^construction^11110000MB1503996K^non-construction_expansion","DATAJSONTEXT":"{\"VERSION\":\"20210903\"}"}]}]
2
1
http://yzt.beijing.gov.cn/am/UI/Login?realm=%2F&service=bjzwService&goto=http%3A%2F%2Fyzt.beijing.gov.cn%2Fam%2Foauth2%2Fauthorize%3Fservice%3DbjzwService%26response_type%3Dcode%26client_id%3D000026681_06%26scope%3Dcn%2Buid%2BidCardNumber%2Breserve3%2BextProperties%2BcredenceClass%26redirect_uri%3Dhttp%253A%252F%252Fyewu.ghzrzyw.beijing.gov.cn%252Fgw%252FssoLogin%252Flogin%3FitemCode%3DCX-CX_004
政务服务> 办事指南
建设工程规划核验(城镇居民建房)
北京市
切换简洁版
-
承诺件
办件类型
-
0
到现场次数
-
20工作日
法定办结时限
-
7工作日
承诺办结时限
办件承诺办结时限说明:(承诺时限为办理流程中“审查与决定”环节的计时时限)
办件承诺办结时限说明:
(承诺时限为办理流程中“审查与决定”环节的计时时限)